PMP Exam Prep: Schedule Basics

Schedule Management Plan

The schedule management plan defines how the project schedule will be developed, monitored, and controlled. It includes:

Key Processes

According to PMBOK, schedule management involves:

  1. Define Activities: Break down work packages into activities.
  2. Sequence Activities: Determine dependencies (e.g., finish-to-start).
  3. Estimate Activity Durations: Use techniques like three-point estimating.
  4. Develop Schedule: Create the schedule model using critical path method.
  5. Control Schedule: Monitor and adjust the schedule as needed.

Example

For a software project, activities might include "Design Database" (5 days), followed by "Develop API" (10 days, dependent on database design). The schedule management plan ensures these are sequenced and tracked properly.